Clean roadway from debris following pavement
removal operations
·
Performed additional concrete patching
identified following pavement removal.
·
Preparatory work prior to paving 1st
layer of asphalt pavement.
·
Continued with landscape restorations
Work Anticipated to be Performed, October 2nd
to October 6th
·
Complete remaining concrete repairs.
·
Continue with landscape restorations.
·
Complete preparatory work prior to paving first
layer of asphalt
·
Pave first layer of asphalt pavement.
Following the removal of the asphalt pavement and observing
vehicles traveling over the areas previously milled, it was determined
additional patching should be completed prior to begin paving operations.
The contractor does anticipate getting all the additional
patching completed by early next week. Once the patching is completed, the
first layer of new asphalt pavement will be paved. Currently the asphalt paving
is scheduled for Thursday of next week.
During paving operations, traffic will be reduced to 1 lane
and vehicles routed around the work area with flaggers. The contractor
will also be working in the Glenview Road / Harlem Avenue intersection.
Please plan accordingly as we anticipate significant travel delays again.
Once the first layer of asphalt pavement is installed, the
amount of dust will be greatly reduced.
Thanks again for all your understanding.