·
Removal of Northbound Detour. 2-way traffic
re-established
·
There will continue to be construction delays as
the road work continues; however, work will be done during working hours with
flaggers
·
Performed pavement milling of the entire
roadway, including intersection of Glenview Road & Harlem Avenue
·
Installed temporary pavement marking tape to
delineate lanes.
·
Swept roadway from debris due to construction
and milling operations.
Work Anticipated to be Performed, September 25th
to September 29th
·
Evaluate pavement following milling and perform
pavement patching as required
·
Complete remaining concrete repairs.
·
Continue with landscape restorations.
·
Depending on work progress, pave first layer of
asphalt pavement near the end of the week.
A majority of the concrete base repairs are completed. The
pavement will be re-evaluated to determine if any additional pavement patching
needs to occur. It is anticipated any additional pavement patching will be
performed next week. Depending on work progress, the first layer of
asphalt pavement will be paved.
The northbound detour from Golf Road to Glenview Road has
been removed with 2-way traffic being re-established. The remaining work will
be performed allowing for 2-way traffic at all times. However, during patching
and paving operations flaggers will be utilized to direct traffic around the
work zone. Travel delays are expected to continue until project completion.
Thanks again for all your patience and understanding as you
utilized alternate routes during the northbound detour.