Installed water main through intersection of
Harlem Avenue & Glenview Road.
·
Continued to install water main south of
Glenview Road to Dewes Street
·
Continued to install water main on the south
portion of the project from Colfax Avenue to Culver Lane
·
Installed tee and valve at intersection of
Colfax Avenue and Nora Avenue in preparation for water main installation in
that area.
·
Performed necessary testing and acquiring needed
approvals prior to performing water service replacements from Colfax Avenue to
Golf Road
·
Potholing / locating of existing underground
utilities prior to water service replacement via directional drill methods.
Work Anticipated to be completed, April 24th to April 28th
·
Continue with water main installation on north
portion of the project from Dewes Street to Linneman Street
·
Perform necessary testing of installed water
main from Glenview Road to Dewes Street
·
Continue with water main installation on south
portion of the project from Culver Lane to Robincrest Lane
·
Perform pavement patching of aggregate trenches
with asphalt
·
Water service replacements from Golf Road to
Colfax Avenue
Harlem Avenue / Glenview Road Intersection Improvements
Thank you for all your patience and understanding regarding
traffic delays and water shut-downs as the work was performed within the
intersection.
The contractor will continue to use two crews to install the
water main from the north and south portions of the project. This will
definitely speed-up the overall project, but does cause traveling along Harlem
Avenue more difficult.
The contractor will begin water service replacements between
Golf Road and Colfax Avenue. Water services will be replaced from the new water
main to the existing valve and box located in front of each home. During the
water service replacement, water to individual homes will be shut-off for
approximately 2-3 hours while the transition from the old service to the new
service is made. The contractor will notify each resident individually
regarding the approximate time and day of the water shut-off prior to turning
off the water.
The water services will be directionally drilled under the
existing pavement. In order to for this work to be performed, the contractor
will be setting up equipment on your lawns and need to park equipment in your
driveways. In order to minimize and potential damage, the equipment will be
placed on sheets to wood. The contractor will notify you prior to any driveway
access restricts and will restore any damage to the lawns.
Thanks again for all your patience as you deal with living
and traveling through a busy construction area.