Detour of North Bound Traffic remains in
effect.
·
Completed concrete base patching on easterly
lanes and intersections.
·
Began concrete base patching on the westerly
lanes and intersections.
·
Lowering of manholes in preparation for pavement
milling of remainder of roadway.
Work Anticipated to be Performed, September 18th
to September 22nd
·
Detour of North Bound Traffic to remain in
effect.
·
Pavement milling of remaining asphalt pavement
including:
o Intersection
of Glenview Road and Harlem Avenue
o Easterly
intersections
o Westerly
travel lanes
o Westerly
intersections
·
Continue with concrete base patching
On Monday and Tuesday next week, the contractor will be
milling the existing pavement along Glenview Road from Harlem Avenue to
Waukegan Road as part of the Harlem Avenue Improvement and the Glenview Road
Improvements. The work has been scheduled to be completed at the same
time to reduce the length of travel delays. We do anticipate some travel delays
along Glenview Road early next week while the work is on-going, please plan
accordingly.
Once the work along Glenview Road is completed, the
contractor will continue to mill the remaining asphalt pavement along Harlem
Avenue. It is anticipated all asphalt pavement milling will be completed by the
end of the week.
Concrete base patching will also continue before and after
the pavement milling. Steel plates will continue to be installed over the
excavations and poured concrete to allow for access to driveways and
intersections to the greatest extent possible.
Thanks again for all your patience as you drive through the
construction site and travel delays anticipated next week while the Glenview
Road work is performed.