Work Continues on Northbound / East Lanes of Harlem Avenue

Work Performed, August 28th to September 1st  
·         Detour of North Bound Traffic has been established and is currently in affect.
·         Set-up signs for detour route and traffic control devices
·         Milled 2-inches of asphalt pavement on north bound / easterly lanes
·         Removed temporary asphalt and gravel previously installed in water main trench on east side of roadway
·         Began pouring permanent concrete base course over water main trench.

Work Anticipated to be Performed, September 5th to September 8th  
·         No work planned over weekend or Monday, September 4th in observance of Labor Day
·         Complete pouring permanent concrete base course over water main trench on east side of roadway
·         Perform additional concrete patching as needed on east side of roadway

During the excavation, concrete installation, and curing period, steel plates will continue to be installed at each driveway and intersection to allow for vehicular access. There will be times when access will not be possible at certain intersections and driveways while construction is on-going.  Access is anticipated to be re-established at the end of each work day.

Thank you for all your patience and understanding as the northbound detour is now in place. We are expecting the detour to remain in place for approximately 1 month.