Friday, September 8, 2017

Work to Begin on West Side of Harlem Avenue

Work Performed, September 5th to September 8th
·         Detour of North Bound Traffic remains in effect.
·         Completed concrete base patching along the east / northbound lanes of Harlem Avenue
·         Continued with concrete base patching along the easterly intersections of Harlem Avenue

Work Anticipated to be Performed, September 11th to September 15th
·         Detour of North Bound Traffic to remain in effect.
·         Concrete base patching completed on the westerly lanes of Harlem Avenue
·         Concrete base patching complete along westerly intersections.

Concrete base patching is continuing to be performed and the northbound detour remains in effect. As previously, steel plates will be installed over the excavations and poured concrete to allow for access to driveways and intersections to the greatest extent possible.